Diley Road Project
Updates
PLEASE USE CAUTION AT ALL TIMES
WHEN DRIVING THROUGH THE WORK AREA
June 30, 2008:
Diley Road Closure # 4: Beginning July 7 and
lasting through August 6 (MAP)
May 29, 2008:
Diley Road Closure # 3: Beginning June 5, 2008
and lasting through June 19 (MAP)
March 31, 2008:
Diley Road Closure # 1: Beginning April 7,
2008 and lasting for 30 days (MAP).
Diley Road Closure # 2:
The second closing
is scheduled for May 5, 2008 thru June 2 +/-,
The schedule is subject to change
due to work conditions (weather, supply deliveries, etc.). The
George J. Igel & Co., Inc., ODOT, and the City of Pickerington are
not responsible for any schedule discrepancies.
March 3, 2008:
Begin installation of sanitary sewers. Traffic will
be maintained through all areas of the work zone.
February 28, 2008:
1. Bid - Construction project bids were
received by the Ohio Department of Transportation in December 2007,
and the project has been awarded to George J. Igel and Company,
Inc. for $13,168,505.76. Work on the project is expected to
begin in mid-February 2008, and is planned for completion in late July
2009.
2. Construction - On-site construction efforts
will be managed by the Ohio Department of Transportation, District 5.
Periodically, the City of Pickerington will post construction progress
documentation on its website for your information, including
construction schedule and detour information, pictures, and other
items. Please check back regularly for additional updates.
3.
Public Information Notices (Notices sent to Diley Road residents) -
Noise Walls;
Project Summary.
|