Diley Road Project

Updates

PLEASE USE CAUTION AT ALL TIMES WHEN DRIVING THROUGH THE WORK AREA

June 30, 2008:

Diley Road Closure # 4:  Beginning July 7 and lasting through August 6 (MAP)

May 29, 2008:

Diley Road Closure # 3:  Beginning June 5, 2008 and lasting through June 19 (MAP)

March 31, 2008: 

Diley Road Closure # 1:  Beginning April 7, 2008 and lasting for 30 days (MAP).

Diley Road Closure # 2:  The second closing is scheduled for May 5, 2008 thru June 2 +/-,

The schedule is subject to change due to work conditions (weather, supply deliveries, etc.). The George J. Igel & Co., Inc., ODOT, and the City of Pickerington are not responsible for any schedule discrepancies.

March 3, 2008:

Begin installation of sanitary sewers. Traffic will be maintained through all areas of the work zone.

February 28, 2008:

1.  Bid - Construction project bids were received by the Ohio Department of Transportation in December 2007, and the project has been awarded to  George J. Igel and Company, Inc. for $13,168,505.76.  Work on the project is expected to begin in mid-February 2008, and is planned for completion in late July 2009.

2.  Construction - On-site construction efforts will be managed by the Ohio Department of Transportation, District 5.  Periodically, the City of Pickerington will post construction progress documentation on its website for your information, including construction schedule and detour information, pictures, and other items.  Please check back regularly for additional updates.

3.  Public Information Notices (Notices sent to Diley Road residents) - Noise Walls; Project Summary.

 